We were proud to be engaged at the design stage for this landmark project. The brief was to provide a full upgrade of the existing kitchen

 

The kitchen design was spread over 2 years both refining and waiting for the right time to take this landmark restaurant off the market.

 

Working in conjunction with Calida on a tight construction program. Both the construction and design teams overcame several challenges presented in the course of the 8 weeks. Include a new exhaust hood mid-project with a lead time of 4 weeks 

 

The final result was impressive that will allow Matt, Ben and their team to deliver  culinary  experiences for another 17 years

 

ARIA SYDNEY | PROJECT PROFILE

LOCATION

DESIGNER

No.1 MACQUARIE ST 

SYDNEY NSW 2000

GEORGE LIVISSIANIS

PROJECT TYPE

DESIGN & CONSTRUCT

PROJECT RANGE

250-500K

AREAS

1 KITCHEN, 1 BAR & KITCHEN

CONSTRUCTION TIME

8 WEEKS